Commissioning starting at Wear Point Wind Farm


Infinergy's Wear Point Wind Farm near Milford Haven, Wales is finally entering commissioning stage! Today will see the start of the commissioning of Wear Point Wind Farm. After long delays all issues regarding the grid connection requirements have now been resolved and we are looking forward to Wear Point Wind Farm generating lots of green electricity very shortly. All four wind turbines are expected to be fully operational by this Friday 16th May.