Developing Wind Farms - Construction

Construction typically takes some six months. Access tracks, the temporary construction compound, foundations, underground cabling and the substation all need to be built, along with the turbines. Of the six month period, the first five months comprise civil works and the remaining month is for turbine erection. The wind farm must also be connected to the grid. The turbines are installed on concrete foundations, with all parts lifted into place by cranes.